Home / News / Industry Information / Installation method of 4WE10 solenoid directional valve

Installation method of 4WE10 solenoid directional valve

Views: 0     Author: Site Editor     Publish Time: 2025-10-28      Origin: Site

Inquire

wechat sharing button
facebook sharing button
twitter sharing button
line sharing button
wechat sharing button
linkedin sharing button
pinterest sharing button
whatsapp sharing button
kakao sharing button
snapchat sharing button
telegram sharing button
facebook sharing button
twitter sharing button
line sharing button
wechat sharing button
linkedin sharing button
pinterest sharing button
whatsapp sharing button
kakao sharing button
snapchat sharing button
telegram sharing button
facebook sharing button
twitter sharing button
line sharing button
wechat sharing button
linkedin sharing button
pinterest sharing button
whatsapp sharing button
kakao sharing button
snapchat sharing button
telegram sharing button
facebook sharing button
twitter sharing button
line sharing button
wechat sharing button
linkedin sharing button
pinterest sharing button
whatsapp sharing button
kakao sharing button
snapchat sharing button
telegram sharing button
sharethis sharing button

4WE10 solenoid directional valve is usually installed on the bottom plate, and the connection method is welding. During installation, the axis must be ensured to be horizontal, and the specific steps and safety regulations in the product manual must be followed. The following are specific installation points:


Installation method: 4WE10 solenoid reversing valve is usually installed on the base plate. This installation method is convenient for fixing and connecting the pipeline system and ensures the stability of the valve during operation.

Connection method: During the installation process, the connection method of 4WE10 solenoid directional valve is usually welding. This requires the installer to have certain welding skills to ensure the sealing and strength of the connection and prevent hydraulic oil leakage.

Installation notes:

Horizontal installation: The axis of the electromagnetic reversing valve should be kept horizontal when installed. Inclined or vertical installation is not allowed. This is to ensure that the valve core inside the valve can move freely without being affected by gravity, thereby ensuring the normal operation of the valve.

Follow the product manual: Before installation, you should read the product manual carefully to understand the structure, working principle and installation steps of the valve. Installation in accordance with the instructions in the manual can avoid valve damage or performance degradation caused by improper operation.

Check the tightness: After installation is complete, the valve should be checked for tightness. The tightness can be confirmed by injecting hydraulic oil into the valve and observing whether there is leakage. If leakage is found, it should be dealt with in time to ensure the normal operation of the valve.

Installation steps (take base plate installation as an example):

Prepare tools and materials: including welding equipment, base plate, bolts, nuts, etc.

Fix the base plate: Fix the base plate in the predetermined position to ensure that the base plate is flat and firm.

Welding valve: Weld the 4WE10 electromagnetic reversing valve to the base plate. Pay attention to keeping the valve axis level during the welding process.

Connect the pipeline: According to the system requirements, connect the hydraulic pipeline to the corresponding interface of the valve. When connecting, make sure the pipe connection is secure and well-sealed.

Inspection and debugging: After installation is completed, inspect and debug the valve. Confirm that the valve moves flexibly, is well sealed and has no leakage.


Related Products

Contact Us
    No. 7, Zhenzhu Road, Shanxia Lake, Zhuji, Shaoxing, Zhejiang
   SARAH-L53@HOTMAIL.COM
    86+17769886871

Product Display

Quick Link

Zhejiang ICP No. 2025171452-1 © 2025 Zhejiang Tenco Hydraulic Machinery Co., Ltd. All Rights Reserved.